The Town of Parker has contracted with Aggregate Industries to perform roadway resurfacing work this summer in two areas in Parker, including Crown Crest Boulevard (between Parker Road and Pine Lane) and Dransfeldt Road (between Lincoln Avenue and Longs Way).
Construction on Crown Crest Boulevard is scheduled to begin in mid-June and conclude in mid-July. Work will then move to Dransfeldt Road, where it will continue until mid-August.
During this time period, we expect lane closures and minor delays Monday through Friday between 7 a.m. and 5 p.m. For additional information on this program or other projects in the Town of Parker, please contact the Engineering and Public Works Department at 303.840.9546.
To view a map highlighting all Town of Parker summer roadway construction scheduled for 2020, visit www.ParkerOnline.org/StreetProjects.