The Town of Parker will begin work on the reconstruction of Nate’ Drive between J. Morgan Boulevard and Hess Road in early April, weather permitting. Completion of this project is planned for late summer 2021.
This project will be completed in two phases. Phase 1 will involve realigning two-way traffic to the east side of Nate’ Drive to allow for the reconstruction of the west half of the roadway. Phase 2 will mirror the first phase with traffic being realigned to the west side to allow for the reconstruction of the east half of the roadway. Once both sides of the roadway have been reconstructed, a final two-inch lift of hot mix asphalt will be paved, followed by pavement marking.
Updates on this project and other Town capital improvement projects can be found online at www.ParkerOnline.org/CIPUpdate. If you have any questions concerning this project, please contact the Town of Parker Engineering Department at 303.840.9546.